What problems should we pay attention to when installing fence cage of lift?

1. ​Wash the foundation surface and install anchor bolts. If the construction lift is installed on the basement floor, a cushion iron must be used below the anchor screws to increase the contact surface between the nuts and the floor to prevent the friction of the nuts on the floor from being lowered.

2. Insert steel plate spacers of different thickness between the chassis and the foundation stone of the anchor bolt to adjust the perpendicularity of the rail frame. So here we have 1 person lift.

3, the installation of three standard sections, using the theodolite to measure the verticality of the guide rail, to ensure that the guide rail in two directions (1/1000) of the vertical degree.

e8589651d06e3882c0d8538e51fca5674. After the vertical adjustment of the guide rail, press the 4 anchor bolts.

5. Adjust the verticality of the fence door frame as above, and tighten the remaining anchor bolts.

6. Install the buffer spring.

7. Bolt the remaining half of the fence to the front half.

8. Adjust the verticality as above, press the anchor bolt, and release the brake of the motor in the cage. (for SC200/200, first install the cage, then install the transmission plate).

9. Lift the cage with a crane and place the cage accurately from the top of the standard section; ​place the two cages separately on the guide rail and slowly place them on the buffer spring. Prepare the drive frame for both cages and adjust the rear wheel and roller to the position with maximum clearance to facilitate the installation of the drive frame. Install a standard section in the base part of the lift with lifting equipment, tighten the connecting bolts, install two groups of drive frames above the respective cage with lifting equipment, empty the connecting pins, and install the cage top guardrail.

10. Reset the brakes.

11. Installation and maintenance. The maintenance section is generally installed in the fourth section,

12. Install two more standard segments. Check and adjust the perpendicularity of the rail frame with the theodolite to make the error of the two directions perpendicular to each other meet the requirements.